Eynesbury Water Storages & Ancillary Works

This project was initiated by due to a new township being developed at Eynesbury, The site was excavated on a green fields site majority in rock, construction works included installation of a two bolted steel panel tanks, 1.4Ml potable water storage tank and a 2.5Ml recycled water tank with large bore inlet and out let pipework that needed to be integrated into the Western Water network. A local chemical dosing system was also installed to provide disinfection to the new towns water supply, along with remote connection via SCADA to Surbiton Park Water Treatment Plant.

 

Client: 

Villa World Group

 

Client contact details: 
Name: Nelson Yeung (Villa Word Group)
Telephone: 0418 711 783
Facsimile: 
Email: 

Consultants: 

SMEC

 

CCB Envico project staff: 
Project Manager: Will Lovell
Site Manager: 
OH&S Representative:
Administrator:  
Average Workforce: 6

 

Contact details: 
Name: Pieter De Villiers 
Telephone: 03 9514 1500 
Facsimile: 
Email:

 

Project duration: 

5 Months